Skip to content
← InsightsExplainer / 2 min read

How Data Centers Get Power

From the transmission grid to the server rack: the path electricity takes into a data center campus, and the people who make each step happen.

How Data Centers Get Power
GridTal Insights / Fig. 09

A large data center can draw as much electricity as a small city. Getting that power to a campus involves the bulk transmission grid, a utility, a high-voltage substation, an on-campus distribution system and layers of backup: each designed, negotiated and operated by different specialists.

Step 1: The grid and the serving utility

Power begins at generating plants and travels across the high-voltage transmission system. Every campus is served by a utility (investor-owned, cooperative or municipal) that decides how and when it can supply new load. In some markets, a grid operator (ISO/RTO) also studies the impact of large new loads.

“From the transmission grid to the server rack: the path electricity takes into a data center campus, and the people who make each step happen.”

Step 2: The load request and studies

A developer submits a request for service, specifying how many megawatts it needs and when. The utility studies whether existing lines and substations can carry that load and what upgrades are required. This is the interconnection process, and it is often the longest step in a project.

Step 3: Agreements and upgrades

If studies show upgrades are needed, the utility and developer agree on scope, cost responsibility and schedule. New transmission lines, reconductoring or substation expansions may follow. Large-load tariffs and electric service agreements set the commercial terms.

Step 4: The campus substation

Most large campuses have their own high-voltage substation, which steps transmission voltage down to medium voltage for distribution around the site. Transformers and breakers can have long lead times, so substation design and procurement often start early.

Step 5: Distribution, UPS and generators

Inside the campus, medium-voltage feeders carry power to each building, where it is transformed again and routed through switchgear and uninterruptible power supplies (UPS) to the IT load. Backup generators (typically diesel today, with growing interest in gas, fuel cells and batteries) keep critical load running through outages.

Step 6: Onsite and behind-the-meter supply

Where grid capacity is slow to arrive, some developers add onsite generation or storage to bridge the gap or supply power permanently. This adds fuel supply, air permitting and generation operations to the project.

The people behind each step

Interconnection managers and utility relations managers lead steps two and three. Power systems, transmission, substation and protection engineers design steps three through five. Energy procurement managers shape supply, onsite generation managers lead step six, and critical power operations teams run the system for decades afterward.

// The GridTal Brief

Power and talent intelligence, monthly.

No spam. Unsubscribe anytime. See our Privacy Policy.

// Read next

The Data Center Interconnection Process, Step by Step

Explainer / 1 min →