Skip to content
// Glossary

Data center power glossary.

The grid, interconnection and energy terms every data center power team uses, defined in plain English and linked to the roles that own them.
High-voltage transmission lines connecting to the grid
  • Behind-the-meter (BTM) power

    Generation located on the customer's side of the utility meter, serving the site directly instead of flowing through the grid first.

  • Bridge power

    Temporary onsite generation that powers a campus until its permanent grid connection is energized.

  • Capacity market

    A market where grid operators pay resources to be available to produce power in future years.

  • Co-location (generation)

    Placing a data center directly next to a power plant so the plant serves the campus with little or no use of the transmission grid.

  • Commissioning

    The process of testing and verifying that electrical and mechanical systems work as designed before operations begin.

  • Critical IT load

    The power drawn by servers, storage and network equipment, as opposed to cooling and building systems.

  • Electric service agreement (ESA)

    The contract under which a utility agrees to deliver power to a customer site, including capacity, ramp schedule and rates.

  • Energization

    The moment new electrical equipment is first connected to a live power source and put into service.

  • Facilities study

    The interconnection study that scopes, prices and schedules the specific equipment and upgrades needed to connect a project.

  • Interconnection agreement

    The contract between a project and the utility or grid operator that sets the terms, costs and schedule for connecting to the grid.

  • Interconnection queue

    The ordered list of generation, storage and large-load projects waiting for a utility or grid operator to study and approve their connection to the grid.

  • Large load

    A single customer, such as a data center campus, whose electricity demand is big enough to require special studies, tariffs or transmission upgrades.

  • Large-load tariff

    Utility rate terms written specifically for very large customers, often including minimum bills, long contract terms and collateral.

  • Microgrid

    A local power system with its own generation and controls that can run connected to the grid or on its own.

  • N-1 contingency

    A reliability standard requiring the grid to keep operating normally after the loss of any single major element.

  • NERC CIP

    The North American Electric Reliability Corporation's Critical Infrastructure Protection standards for securing grid assets.

  • Point of interconnection (POI)

    The physical location where a project's facilities connect to the utility's transmission or distribution system.

  • Power purchase agreement (PPA)

    A long-term contract to buy electricity, and often its environmental attributes, from a specific generation project.

  • Protection and controls (P&C)

    The relays, settings and control schemes that detect faults and isolate equipment to keep the power system safe.

  • PUE (power usage effectiveness)

    Total facility power divided by IT equipment power; a measure of data center energy efficiency.

  • RTO / ISO

    Regional transmission organizations and independent system operators that run the grid and wholesale power markets across multiple utilities.

  • SCADA

    Supervisory control and data acquisition: the systems that monitor and control electrical equipment remotely.

  • Substation

    A facility that steps voltage up or down and switches power between lines, using transformers, breakers and protection equipment.

  • System impact study

    An engineering study that tests how a new project would affect grid reliability and identifies the upgrades needed to connect it.

  • Transformer lead time

    The time between ordering a power transformer and receiving it, which has stretched to multiple years for large units.

Hiring for one of these areas? Browse role guides or request talent.