Top 3 this week
1. AWS emerges behind a $264M Washington land deal for up to 21 data center buildings. 2. Google backstops TeraWulf’s Kentucky campus, contracted to Anthropic under a $19B lease. 3. At least 33 communities back data center restrictions as local approvals get harder.
Data center deals & projects
AWS reveals its $264M Washington land play: AWS confirmed it is behind the nearly 1,000-acre West Richland deal, where preliminary plans envision up to 21 data center buildings. That is a substantial development footprint—not yet an operating campus. mynorthwest.com
“AWS and Microsoft add land, Google backs TeraWulf, and voters remind developers that financing is only one permission slip.”
Microsoft buys 616 acres in Iowa: Microsoft purchased farmland near Woodward in Dallas County for $95.5 million, with a data center campus planned. The purchase adds a concrete site to its development pipeline, but the snippet gives no power capacity or delivery date. datacenterdynamics.com
Google puts its credit behind TeraWulf: Google will backstop anticipated debt financing for TeraWulf’s Justified Data Campus in Hawesville, Kentucky, which has a $19 billion, 20-year Anthropic lease. Google’s credit support strengthens the project’s route to competitive financing. datacenterdynamics.com
OpenAI's Georgia campus reaches the site-plan gate: Effingham County scheduled a November 3 site-plan vote for Project Camellia, with six buildings across approximately 1,347 acres proposed by OpenAI affiliate Octans GA LLC. The application advances the review process; the source does not establish an approval. wtoc.com
Power coming online
PJM's connection agreements aren't becoming plants fast enough: Only 25 GW of more than 100 GW of generation projects receiving grid connection agreements since 2020 have been built, according to Reuters. Approvals alone cannot meet data center demand when construction and equipment remain bottlenecks. reuters.com
PJM's backstop procurement could shrink sharply: PJM filed a revised reliability backstop proposal after FERC rejected most of its initial plan; analysts say procurement could fall from an initial 6,800 MW target to as little as 630 MW after utilities lowered large-load forecasts. Forecast revisions can materially change how much capacity gets procured. utilitydive.com
DTE sells Vantage to fund utility investment: DTE agreed to sell its non-utility business for about $3 billion, supporting roughly $44 billion of planned investment over five years, including spending for data center demand. The deal redirects capital toward the regulated infrastructure large loads need. reuters.com
Alliant contracts 3,400 MW of data center demand: Alliant has contracted with five large data centers expected to be running by 2031 and increased its 2027–2030 capital program 19% to $15.9 billion. Contracted demand is translating into a larger utility construction agenda—not proof that those loads are already online. industrialinfo.com
Entergy maps more than 1,000 transmission miles: Entergy plans more than 1,000 miles of transmission, primarily in Louisiana and Texas, with about a third of the mileage already under construction. The lines support industrial customers and data centers, putting transmission execution directly on the growth path. benzinga.com
Senate proposal could raise data center transmission charges: Grid Strategies estimates a proposed Senate bill could produce $55 billion in data center transmission charges over 10 years—$35 billion above current arrangements—if enacted. The proposal would materially change the cost of grid access for large computing facilities. techtarget.com
Roadblocks & policy
Voters put restrictions on the buildout: At least 33 communities voted for data center restrictions, including moratoriums, regulations and bans, according to the tracker cited by The Detroit News. Local voter consent is becoming a harder development gate. detroitnews.com
Bartholomew County swaps automatic permission for individual review: Commissioners moved data centers from permitted to conditional use in designated zoning districts, requiring case-by-case Board of Zoning Appeals approval. Eligible zoning no longer means an automatic path to build. therepublic.com
Davidson County chooses rules over a moratorium: North Carolina’s Davidson County adopted data center zoning regulations on October 26 while rejecting a proposed four-month moratorium. Development remains possible, but under a new local rulebook. hpenews.com
Sangamon zoning approval remains under legal challenge: A judge took dismissal motions under advisement on October 30 in a lawsuit seeking to overturn the county’s April 7 data center zoning approval. An approval on paper does not end entitlement risk. illinoistimes.com
New on the project tracker
Octans GA LLC · Project Camellia (Near Rincon, Effingham County, GA, Update) Georgia tracker
Microsoft · Dallas County data center campus (Near Woodward, Dallas County, IA, Update) Midwest tracker
Trammell Crow Co. · AWS Lewis and Clark Ranch campus (West Richland, county not stated, WA, Update) Pacific Northwest tracker
TeraWulf · Justified Data Campus (Hawesville, county not stated, KY, Update) Southeast tracker
Amazon Web Services · Hobart campus (Hobart, county not stated, IN, Update) Midwest tracker
What it means for hiring
Alliant’s 3,400 MW of contracted data center demand and Entergy’s more than 1,000 planned transmission miles point toward demand for utility capital-program, transmission delivery and interconnection leaders. PJM’s gap between connection agreements and completed generation puts a premium on equipment procurement and construction execution. With at least 33 communities backing restrictions, permitting and community-engagement experience belongs in the leadership brief—not just the consultant scope.
Follow the source links for full details. Hiring for grid or data-center power roles? Talk to GridTal.