Meta
Lebanon campus — Phase 1
Lebanon, Boone County, INMidwest
Meta said it hopes to bring the first phase online by late 2027 or early 2028.
- Reported capacity
- Not reported
- Reported investment
- $10B

Tracker updated 2026-11-13 · 8 forecast milestones
Align site development, power availability and commissioning milestones. Define who owns utility coordination, interconnection execution and the handoff into operations.
Define utility commitments, queue execution and escalation ownership before setting energization targets.
Connect grid studies, substation design and protection expertise to the project’s power architecture.
Set acceptance criteria, operational handoff and critical-power accountability ahead of service.
Project activity informs team planning; current vacancies are listed separately in Open Roles.
Dated project updates, not unique-campus counts. Capacity refers to the individual milestone; forecasts retain their source timing.
Meta
Lebanon, Boone County, INMidwest
Meta said it hopes to bring the first phase online by late 2027 or early 2028.
Meta
Aiken County, SCCarolinas
Meta's 715,000-sq-ft AI-optimized facility was expected to be operational in spring 2027.
Meta
Cheyenne, WYMountain West
Reporting on Meta's Cheyenne data center said the 715,000-sq-ft facility is expected to go online in 2027.
Meta
Mason County, KYSoutheast
The October report describes an approved Meta hyperscale data center that will occupy more than 2,000 acres, without stating the approval date.
Meta
Eagle Mountain, Utah County, UTMountain West
Meta announced it is further expanding its Eagle Mountain campus, bringing its total Utah data center investment to over $3 billion.
Meta
Rayville, LASouth Central
Meta more than doubled its Richland Parish 'Hyperion' AI data center, raising planned spend to $50 billion and site size past 3,200 acres.
Meta
Montgomery, ALSoutheast
Meta's Montgomery, Alabama data center campus grew to more than 1.3 million square feet, pushing total investment to $1.5 billion, nearly double the original figure.
Meta
El Paso, El Paso County, TXTexas
Meta subsidiary Wurldwide LLC filed to add 12 new data center buildings (25.9 million sq ft total) under 'Project Seafox' at its El Paso campus, with roughly 600 acres of new development and five owner substations.
Meta
El Paso, El Paso County, TXTexas
Meta confirmed its El Paso Data Center would grow to 1 gigawatt of capacity, increasing its investment to more than $10 billion and expecting more than 4,000 peak construction workers on site.
Meta
El Paso, TXTexas
Meta increased its El Paso data center investment from $1.5 billion to more than $10 billion and confirmed the site will scale to a full 1 gigawatt.
Meta
Lebanon, INMidwest
Meta announced plans in February 2026 to invest 0 billion in a new gigawatt-scale data center campus in Lebanon, Indiana.
Meta
Lebanon, Boone County, INMidwest
Meta broke ground on a 13-building, four-million-square-foot campus on 1,500 acres in the LEAP Research and Innovation District.
Meta
Graniteville/Vaucluse, Aiken County, SCCarolinas
Aiken County officials said completion of Meta's $800 million-plus Sage Mill Industrial Park data center is scheduled for 2027, alongside incentive approvals for two additional area data center projects.
Meta
El Paso, TXTexas
Meta broke ground on a nearly 1.2 million-square-foot AI-optimized data center in El Paso, its third Texas facility, able to scale to 1GW with an initial $1.5 billion investment.
Meta
New Albany, Licking County, OHMidwest
Meta confirmed its 'Prometheus' gigawatt AI supercluster is being built at its New Albany, Ohio data center campus, expected online in 2026.
Meta
Aiken County, SCCarolinas
Meta's regional community development manager told the Aiken Rotary Club that affordable land, pro-business climate, streamlined approvals and a shovel-ready site drew the $800 million project to Aiken County.
Meta
Graniteville/Vaucluse area, Aiken County, SCCarolinas
Meta said a 100MW solar farm developed by Silicon Ranch in Orangeburg County, coordinated with Santee Cooper and Central Electric Power Cooperative, will anchor power for its $800 million Aiken County AI data center.
Meta
Aiken County, SCCarolinas
Local coverage detailed Meta's $800 million data center under construction at Sage Mill Industrial Park, expected to transform the Aiken County economy.
Meta
Richland Parish, LASouth Central
Meta said the Richland Parish site will deliver 5GW of compute for its Hyperion AI cluster, part of over $50B in Meta data center investment in Louisiana.
Meta
Middleton Township, Wood County, OHMidwest
Meta announced a new $800 million, 715,000-square-foot AI-optimized data center in Middleton Township, Wood County, its second Ohio site.
Meta
Kuna, Ada County, IDPacific Northwest
Meta reached 'peak construction' with 1,400 workers on-site at its Kuna data center; the facility is now expected to be operational by end of 2026, a year later than planned.
Meta
Los Lunas, Valencia County, NMMountain West
Meta's Los Lunas Data Center fact sheet shows over $2.5 billion invested in New Mexico and more than 400 operational jobs supported once complete.
Meta
Mesa, AZArizona
Meta announced its Mesa data center, begun in 2021, is now serving traffic and will represent more than $1 billion in state investment once fully built.
Meta
Los Lunas, NMMountain West
Meta sought village approval for a roughly $800 million, two-building AI-focused expansion of its Los Lunas data center campus.
Meta
Richland Parish, LASouth Central
PRNewswire release confirmed construction on the Richland Parish facility is expected to continue through 2030.
GridTal is the retained executive search firm for data center power.